Changes between Version 3 and Version 4 of KhairulGSOC2010Schedule

Show
Ignore:
Timestamp:
06/29/10 04:11:35 (12 years ago)
Author:
cotto
Comment:

updates after meeting with khairul

Legend:

Unmodified
Added
Removed
Modified
  • KhairulGSOC2010Schedule

    v3 v4  
    55Prototype the API. 
    66 
    7 Status: 
     7Status: completed on schedule 
    88 
    99== week 2 (May 31st - June 6th) == 
     
    1111Implement the base tool. 
    1212 
    13 Status: 
     13Status: completed on schedule 
    1414 
    1515== week 3 (June 7th - 13th) == 
     
    1717Implement simple instruments. 
    1818 
    19 Status: 
     19Status: completed on schedule (tracer.nqp) 
    2020 
    2121== week 4 (June 14th - 20th) == 
     
    2323Code review, tests and documentation. If possible, add GC hooks. 
    2424 
    25 Status: 
     25Status: review completed, tests insufficient and documentation nonexistent 
    2626 
    2727== week 5 (June 21st - 27th) == 
    2828 
    29 Instrument Query API (2-3 weeks planned). 
     29Instrument Query API (2-3 weeks planned).  Note: Instrument Query API was found to be unnecessary. 
    3030 
    31 Status: 
     31Status: limited progress (external circumstances) 
    3232 
    3333== week 6 (June 28th - July 4th) == 
    3434 
    35 Instrument Query API (2nd week). 
     35Instrument Query API (2nd week).  Note: Goal changed to increasing test coverage and implementing GC instrumentation. 
     36 
     37Status:  
    3638 
    3739== week 7 (July 5th - 11th) ==